Glakos Paints Co. Ltd. is demanding payment of Kshs 10,091,895 from Uasin Gishu County Governor Jonathan Bii Chelilim. The company demanded the sum after the construction project was completed, but did not pay the final required and agreed amount.
A contract for building an Airbnb facility at Hazina Estate in Eldoret is associated with this amount.
A letter from Kimaru K. Kimutai and Co. Advocates confirms the construction project’s completion.
Despite meeting all agreed-upon milestones, we have not yet received payment.
The letter claims that Chelilim has made multiple promises but has failed to fulfil his financial obligations, with attempts to collect the debt ignored.
The outstanding payment has been overdue for over three years.
The advocates are demanding that the governor pay the amount due, along with additional interest of Kshs 4,500,000 and collection fees of Kshs 1,000,000, within seven days.
If he fails to comply, legal action will follow, with costs and consequences incurred at his expense.